The typical order
- Design and quotation approved, order placed
- Removal of the old kitchen
- Any structural work (openings, partitions)
- Plumbing and electrics
- Floors, walls, plastering, base coat of paint
- Unit installation
- Templating and worktop fitting (mineral worktops)
- Splashback, connections, appliances
- Finishing and adjustments
Anticipate lead times
Manufacturing lead times for units and mineral worktops set the installation date. Time the removal to match delivery to limit the period without a kitchen.
Living through the works
Set up a temporary kitchen (microwave, portable hob, fridge) in another room and protect nearby floors and furniture from dust.
Indicative guide. Each project is studied by the professional.